Calculate Your Building Permit Fee
Fee Calculation Result
Tampa Campus Fee Schedule
📊 Cumulative Tier System
Each portion of your project is charged at its tier's rate. We add up all portions to get your total fee.
Example: $75,000 project
• First $5,000: $150.00
• Next $20,000: $20,000 × 2.75% = $550.00
• Next $50,000: $50,000 × 2.25% = $1,125.00
Total Fee = $1,825.00
Off-Campus Fee Schedule
📊 Cumulative Tier System
Off-campus projects have higher rates. Each portion is charged at its tier's rate, then summed.
Example: $75,000 project
• First $5,000: $200.00
• Next $20,000: $20,000 × 3.25% = $650.00
• Next $50,000: $50,000 × 2.75% = $1,375.00
Total Fee = $2,225.00
When Building Permits Are Required
Any new building, structure, or addition to an existing building
Significant modifications to existing structures including interior remodels, exterior changes, and structural modifications
Installation or replacement of HVAC systems, electrical upgrades, plumbing modifications, and gas line installations
Full roof replacements and major roof repairs or modifications
Projects involving structural changes, load-bearing walls, or foundation work
New doors, windows, siding, or significant exterior modifications
New tenant spaces, laboratory buildouts, and specialized interior installations
Installation or modification of fire alarms, sprinkler systems, and emergency systems
ADA-related modifications including ramps, elevators, and accessibility features
Installation of permanent equipment, apparatus, or systems requiring structural support